Nassau House Association, Inc. Board of Directors Workshop Meeting Monday, September 22, 2003 Board Present:
Roy Regeski, Marie Kastenbauer, Rick Larrabee Absent:
Adda Manosalvas, Preston Scroggin Roy opened the meeting
with Marie making a motion and seconded by Rick to accept the last minutes
meeting. Insurance Review: Tabled. Painting: Rick will give the
board a figure on time and material on painting the railings in the stairwell at
the next meeting. Vent structure
on Roof: Vent has been
delivered. Now waiting for installation. Windows: PH-3
Tabled - No response from owner. Cable T.V. To be installed
Tuesday or Wednesday for owners who do not have cable TV. Roof antenna will be
taken down. Cost to be paid by the
association. A monthly fee will
also be paid by the association at $24.95 per month. Security Cameras: Tabled till next
meeting. Parking: Pompano Beach City
Manager sent a letter to the Nassau House stating that cars may be parked in the
Riverside Parking Lot at a cost of $30.00 per month.
Monthly passes may be purchased at City
Hall. Parking has become a serious
problem. when painting is completed
the board will strictly enforce the rules.
Owners parking in guest spots will be towed at owner’s expense as will
guest cars without guest passes on dash board.
All owners MUST PARK IN THEIR OWN SPACE OR RENTED SPACE.
NO MORE GUEST PARKING. Unit #608
catwalk Door: Owner will replace the
existing glass door. Occupancy in
Units: Tabled. Fire Pump: A new standpipe has been
installed on the street side of the bldg.
Electric box in maintenance shop now also working.
Circuit Breakers: Meter room circuit breakers
are going bad and could become dangerous. Some of the breakers have been replaced.
AAA Electric showed Roy where the wires going
into the circuit breakers need to be tightened
up to prevent the burning of the circuit breakers.
This would be an interim fix until all circuit breakers can be replaced.
Roy suggested that he, Renny and Rick could go up to the main meter rooms
and tighten the wires sometime.
Board will look further into this problem as a priority.
Cost could range from $400 to $600 per unit.
Tabled for now. Front Entrance Lights: Lights at front sign, the
front tree base and posts in ground need to be replaced. New PVC conduit needs
to be installed in ground with new boxes and weatherproof lenses.
Cost $2,670.00 Tabled for till Adda returns. Breezeway Door Window
Panel: After a board discussion,
board decided to leave the screen panel in place for now. 9/22/03 |